Sharepoint 2010 Projects Rollout Plan check list

“Day of” PlanThe “Day of” plan should include the following:
  • A detailed description, including cross-references to all “parent” configuration management database (CMDB) document numbers (including change request, project, and maintenance request numbers).

  • A high-level work breakdown that includes start and end date/time for all major tasks and milestones, plus an overall duration for the work plan.

  • A high-level description of any dependencies, issues, and concerns.

  • A logistics plan, including staffing, escalation process, and outline of communication method.


Build Plan
  • An outline of the steps required to build the change.

  • Setup list to deploy the change.

  • This might involve
    • Building a software bundle

    • Requesting special backups

    • Researching a hardware modification

    • Producing new or amended documentation

    • Confirming receipt of and staging hardware and software

    • Preparing to train support and operations staff on the new or amended release, or a combination of such tasks.


“Day of” Test Plan
The “Day of” test plan should include the following:
  • Vendor and user testing.
  • Plans to have a different person perform the test than the person who built and implemented the change.

  • Testing to cover performance and security, as well as functionality.

  • Log files of when the work is complete and documentation of any discrepancies between expected and actual results.


Contingency Plan
The contingency plan should include the following:
  • Details of the back out and recovery plan.
  • This should include an overall description of the plan, the length of time required to back out, and the latest possible date/time for a go/no-go decision to back out.

Contact Information
The contact information should include:
  • Primary update contact information, including business telephone, home telephone, and pager.

  • Secondary update contact information, including business telephone, home telephone, and pager.

  • Primary testing contact information, including business telephone, home telephone, and pager.

  • Secondary testing contact information, including business telephone, home telephone, and pager.

  • Executive sponsor communications plan and contacts.

Transition Plan
The transition plan should include:
  • An outline of the steps required to transfer responsibility for the deployed release to the support and operations staff.

  • The steps to update any impacted release documentation.